Timeline

March 2012
3/2   - Toured several models & chose neighborhood
3/3   - Put deposit down to reserve our lot
3/4   - Signed contract & made initial selections
3/5   - Met with NVR Rep
3/7   - Put our "Sold" sign up
3/20 - Guardian Appointment
3/23 - Design Center Appointment

April 2012
4/3   - Locked-in our final selections
4/19 - Building permit approved

May 2012
5/7   - Pre-construction meeting
5/10 - Broke ground & poured footers
5/11 - Poured basement walls
5/15 - Waterproofed foundation
5/21-5/25 - Underground plumbing installed and framing delivered

June 2012
6/6   -  Sump Pump Installed & Plumbing Inspection passed
6/9   -  Framing began
6/13  - First floor framed
6/18  - Second floor framed
6/20  - Roof trusses
6/24  - Roof finished and most of the windows installed
6/25  - Plumbing began, shingles installed, and rest of windows installed
         - Locked in interest rate at 3.25% by paying .625 points with a VA Loan
6/27  - Concrete poured in garage and basement
6/28  - Basement gets framed

July 2012
7/2    - Electrician installation
7/3    - Guardian installation
7/7    - Insulation installed
7/9    - Pre-drywall meeting
         - Brick started getting installed
         - Garage door installed
7/10  - Drywall begins

August 2012
8/6  - Final Walk-Through 12:00pm
       - Closing 2:30pm
8/7  - We got the keys!

2 comments:

  1. Hey! We are scheduled to close on the same day! :)

    ReplyDelete
    Replies
    1. That makes me nervous! You are I much further along in the process than I am!! I think there are t least two other bloggers with the same closing date too!

      Delete